Executive Summary
- The Data Centre Covenant, announced in October, can allow for exceptionally strategic projects to run temporary on-site generation until a grid connection is secured.
- It will also judge on-site plants that run for years against environmental standards, local impact, and more,
- Here, Alex Marshall, Group Business Development and Marketing Director, at Clarke Energy, discusses planning for a data centre’s power life span.
With developers facing waits for grid connection that can often run into years, temporary on-site generation has been proposed by the UK government as a quicker way to get projects up and running.
However, ‘temporary’ generation equipment like gas engines can have working lives of 15 years or more, long after the grid connection (theoretically) arrives.
Developers therefore need to consider how they can best put that equipment to use beyond the initial bridging period and plan accordingly to maximise return on their investment.
The UK Government’s Data Centre Covenant, published as part of its October budget, has made the issue more pressing. It allows for exceptionally strategic projects to run temporary on-site generation until a connection is secured, albeit under a tightly controlled framework.
The Covenant also sets out five tests that strategic data centres will be expected to meet, and which on-site plants that run for years will be judged against, including on environmental standards and impacts on local communities. Considerations that are particularly relevant to on-site generation that may remain in operation for years to come.
However, with connection delays hard to forecast, and unprecedented AI workloads having shown that demands can grow before a connection arrives, developers installing bridge power should be asking now what that gas engine will do in year five, year 10 and year 15.
Bridge power is not backup power
For context, backup generators run for short periods during outages and testing, while generation installed to bridge a connection delay may run continuously for years and carry the facility’s everyday load.
That changes the engineering, making factors such as equipment selection, maintenance regimes, fuel supply, efficiency and emissions central design questions. Diesel standby sets are rarely suited or permitted to run that way (Environment Agency and Natural Resources Wales, n.d.), whereas gas engines designed for continuous operation are.
The economics change too, as treating bridge plant as disposable means writing off a long-life asset after a fraction of its working life. The better question then is what the plant does once the grid arrives?
One system, not three purchases
A grid connection does not have to make on-site generation redundant. Generation, battery energy storage systems (BESS), controls and the eventual grid supply can be designed from the outset as one system.
Generation provides sustained, dispatchable power, batteries respond quickly and handle short-duration balancing, and the grid becomes another supply option when capacity arrives. Controls decide how the three can work together.
After connection, the generation can move to resilience, peak management or other duties, depending on the site’s commercial arrangements.
This is the basis of the Structured Transition Model. A site can start with on-site generation for speed to power, add storage and other technologies over time, and then change the role of its generation once the grid connects. Lower-carbon fuels can then follow as they become viable.
While nobody can predict a site’s energy mix 15 years ahead, developers can make provisions now that will let the infrastructure adapt without a rebuild once those options become available.
Using the heat
The Covenant states that L=long-running generation will be judged on environmental performance, and the largest gain usually comes from using energy that is already being consumed. A gas engine typically converts around 40 to 45% of its fuel energy into electricity, while most of the rest leaves as heat.
Combined Heat and Power (CHP) recovers it, and Combined Cooling, Heat and Power (CCHP) uses absorption chillers to turn it into cooling, after which total fuel utilisation can reach 85% or more.
For data centres, cooling is the output that matters, and cooling produced from recovered heat is electricity the chillers do not draw. Surplus heat can also supply a local heat network, which speaks directly to the Covenant’s community and environmental tests.
Measuring the right thing
Power Usage Effectiveness (PUE) compares total facility energy with the energy used by IT equipment. While it is a useful measure of the building, it says nothing about how efficiently the power was produced, how much carbon it carried or whether waste heat was used. A site running on-site generation can post a strong PUE while discarding more than half of its fuel energy as heat.
But better measures already exist such as Energy Reuse Factor (ERF) and Carbon Usage Effectiveness (CUE), developed by The Green Grid and now published as ISO/IEC 30134 standards, which capture heat reuse and carbon intensity (ISO/IEC, 2021; ISO/IEC, 2022).
Developers running on-site generation should report against them alongside PUE. Over time, renewable gases such as biomethane can also lower the carbon intensity of the fuel itself where supply is available.
Provisions to make before construction
The cheapest upgrades are nearly always the ones that can be planned before a site is built. Reserve space for battery storage, heat recovery and emissions-abatement equipment, specify modular electrical infrastructure and control systems that can take additional assets, check fuel supply options, heat offtake opportunities and the permits needed for each operating mode the site may use over its life.
While some of these might look secondary when the priority is getting a facility live., all of them would be expensive for an operator to retrofit.
The investment case should then reflect the full working life of the plant, not its first years. The Covenant’s provision for temporary generation is a sensible response to an immediate problem and, for developers, the value lies in a plant that stays useful after the grid arrives. A grid connection should mark a change in the plant’s role, not the end of its usefulness.